2. About the peak cut operation check

Perform peak cut control and check whether or not the air-conditioning units are operating or set as specified below for each control
level.
Change the target electricity values in [Function1] - [Peak cut control] in Administrator Web and then perform control at each peak cut
level.
[Example] When checking the operation at peak cut level 2
Normal settings
To check the capacity save amount of outdoor units, use Maintenance Tool.
Note: After performing the operation check, return the settings to the original settings.
Operation check at peak cut level 2
94