Fujitsu 9363005011 Installation Manual page 5

Ceiling suspension type

Advertisement

3. DRILLING THE HOLES AND ATTACHING
THE SUSPENSION BOLTS
(1) Drill ø25mm holes at the suspension-bolt locations.
(2) Install the bolts, then temporarily attach Special nuts
A and B and a normal M10 nut to each bolt. (The
two special nuts are provided with the unit. The
M10 nut must be obtained locally.) Refer to Fig. 10.
Bolt Strength
980 to 1,470 N (100 to 150 kgf)
Fig. 10
Ceiling panel
10 to 15 mm
[If using anchor bolts]
(1) Drill holes for anchor bolts at the locations at which
you will set the suspension bolts. Note that anchor
bolts are M10 bolts (to be obtained locally).
(2) Install the anchor bolts, then temporarily attach spe-
cial nut "B" (included) and a locally-procured M10
nut to each of the bolts. (See Fig. 11.)
Anchor-Bolt Strength 980 to 1,470 N (100 to 150 kgf)
Fig. 11
Ceiling
M10 Anchor Bolt
(Obtained locally)
4. INSTALLING THE INDOOR UNIT
(1) Lift unit so that suspension bolts pass through the
suspension fittings at the sides (four places), and
slide the unit back. (See Fig. 13.)
Fig. 12
Ceiling
Special nut A (Included)
Special nut B (Included)
M10 Nut (Obtained locally)
Special nut B
(Included)
M10 Nut
(Obtained locally)
Wall
Fig. 13
(2) Fasten the indoor unit into place by tightening-up
the special "B" bolts and the M10 nuts. Make sure
that unit is secure and will not shift back and forth.
[For Half-Concealed Installation]
When installing the indoor unit in a semi-concealed
shape, make sure to reinforce the insulation of the unit
on all sides. Drops of water may fall from the unit if it
is not thoroughly insulated.
Fig. 14
In order to check the drainage, be sure to
check a level during installation of the
indoor unit. If the installation site of the
indoor unit is not level, water leakage
may occur.
– 5 –
Ceiling panel
INDOOR UNIT
Glass wool insulate
(10 to 20 mm thick)
INDOOR UNIT
(Top view)
Ceiling panel
Wall
Wall