York YLAA0041 Installation Operation & Maintenance page 120

Air-cooled scroll chillers with brazed plate heat exchanger style b (60 hz) 4 to 12 fan 40 ton to 230 ton 140 kw to 800 kw
Hide thumbs Also See for YLAA0041:
Table of Contents

Advertisement

Section 5: Technical data
1. Read instructions in their entirety before begin-
ning installation.
2. Isolators are shipped fully assembled and are to be
positioned in accordance with the submittal draw-
ings or as otherwise recommended.
3. Set isolators on floor, housekeeping pad, or sub-
base, ensuring that all isolator centerlines match
the equipment mounting holes. The VMC group
recommends that the isolator base ("A") be in-
stalled on a level surface. Shim or grout as re-
quired, leveling all isolator bases to the same
elevation (1/32 in. maximum difference can be
tolerated).
D
120
Installation of Neoprene vibration isolators
("B")
C L
4. Bolt or anchor all isolators to supporting structure
utilizing base hrough holes ("B").
5. Remove top bolt and top washer. Place equip-
ment on top of isolators so that mounting holes
in equipment or base line up with threaded hole
("C").
6. Reinstall top bolt and washer and tighten down.
7. Installation is complete.
D
("C")
SECTION D-D
Form 150.72-ICOM6
Issue date: 12/19/2023
TOP BOLT
TOP WASHER
("B")
C L
("A")
Johnson Controls
LD13762B