Chapter 5: Activating, Commissioning and
Configuring the System
After the solar system is installed, it is important to activate and commission the solar
system. Activation and commission of the system is performed using the inverter
SetApp mobile application.
During the activation and commissioning, the inverter discovers and communicates
with all connected components in the solar system, such as: optimizers, peripheral
communication devices and other linked inverters. When commissioning is performed,
the user is required to set the grid parameters and backup Voltage information (if used).
Before starting the activation and commissioning, verify all the communication
hardware is properly connected.
Before arriving at the site, download SolarEdge SetApp application to your mobile
device from Apple App Store or Google Play.
Before activation and commissioning, download the SetApp application from:
For downloading SetApp, Internet connection, one-time registration and logging are
required. No registration is required for using the SetApp.
IMPORTANT NOTE!
It is possible to perform DC commissioning on the inverters before completing
the AC connection to the electrical grid. DC commissioning, also referred to as
"commissioning from the sun", is performed in daylight using SolarEdge
SetApp mobile application.
SE330K Inverter P/N: SE330K-xxxxxxxxx
Chapter 5: Activating, Commissioning and Configuring the
System   66