 13.  Place the ferrite beads on the wires and close them. Make sure the DC labeled ferrite bead is placed on 
the DC wires and the AC labeled ferrite bead is placed on the AC wires.    
 14.  Close the inverter cover.
 15.  Configure the system to the required application as described in System Configuration on page 62
 16.  Perform the commissioning steps as described in Commissioning the Installation on page 55.

9V Battery Replacement

If Warning 8: Connection Unit Low 9V Battery is displayed in the main status screen, replace the 9V 
battery in the StorEdge Connection Unit.
 1.  Turn OFF the inverter ON/OFF switch, and wait until the LCD indicates that the DC voltage is safe 
(<50V), or wait five minutes before continuing to the next step.
WARNING!
If you cannot see the inverter panel, or if a malfunction is indicated on the LCD panel, wait five
minutes for the input capacitors of the inverter to discharge.
Si vous ne pouvez pas voir l'écran de l'onduleur ou si un dysfonctionnement est indiqué sur
l'écran LCD, attendez cinq minutes pour que les condensateurs d'entrée de l'onduleur soient
déchargés.
 2.  Turn OFF the StorEdge Connection Unit and the AC switch of the distribution panel. 
 3.  Open and remove the StorEdge Connection Unit cover.
 4.  Open and remove the transparent internal cover.
 5.  Remove the battery from the upper board of the StorEdge Connection Unit and replace with a new 
standard 9V battery.
 6.  Close the StorEdge Connection Unit covers.
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0
Appendix B: Replacing and Adding System Components
Figure 42: The battery holder
91

Advertisement

Table of Contents
loading

Table of Contents