York YLAA0041 Manual page 107

Air-cooled scroll chiller
Hide thumbs Also See for YLAA0041:
Table of Contents

Advertisement

FORM 150.72-ICOM6
ISSUE DATE: 08/03/2022
2 IN. DEFLECTION ISOLATOR INSTALLATION AND ADJUSTMENT
1. Read instructions in their entirety before begin-
ning installation.
2. Isolators are shipped fully assembled and are to be
positioned in accordance with the submittal draw-
ings or as otherwise recommended.
3. Set isolators on floor, housekeeping pad, or sub-
base, ensuring that all isolator center lines match
the equipment mounting holes. The VMC group
recommends that the isolator base plates ("B")
be installed on a level surface. Shim or grout as
required, leveling all isolator base plates to the
same elevation (1/4 in. maximum difference can
be tolerated).
4. Bolt or anchor all isolators to supporting structure
utilizing base plate through holes ("C") or weld
base plate to supporting structure with 3/8 fillet weld
2 in. long at 4 in. on center around entire base
plate or as engineered for specific load and or field
conditions.
5. Isolators are shipped to the job site with (2) re-
movable spacer shims ("E") between the top plate
and the housing. These shims must be in place
when the equipment is positioned over the isola-
tors.
6. With all shims ("E") in place, position equipment
on top of plate ("A") of isolator. Bolt equipment
securely to top plate of isolator using a minimum
of (2) 5/8 UNC A325 grade 5 SAE bolts or weld
("A")
("E")
JOHNSON CONTROLS
("G")
("E")
C L
WASHER
("F")
equipment or bracket to the top plate ("A") of iso-
lator with a minimum of 3/8 fillet welds 2 in. long
at 3 in. on center for a minimum total weld of 10
in. (All sides of equipment or bracket resting on
top plate ("A") must be welded).
7. The adjustment process can only begin after the
equipment or machine is at its full operating
weight.
8. Back off each of the (4) limit stop lock nuts ("F")
on isolators 1/2 in.
9. Adjust each isolator in sequence by turning spring
adjusting nuts ("G") one full clockwise turn at a
time. Repeat this procedure on all isolators, one
at a time. Check the limit stop lock nuts ("F")
periodically to ensure that clearance between the
washer and rubber grommet is maintained. Stop
adjustment of isolator only when the top plate
("A") has risen just above the shim ("E").
10. Remove all spacer shims ("E").
11. Fine adjust isolators to level equipment.
12. Adjust all limit stop lock nuts ("F") per isolator,
maintaining a 1/4 in. to 3/8 in. gap. The limit stop
nuts must be kept at this gap to ensure uniform
bolt loading during uplift (as the case when equip-
ment is drained).
13. Installation is complete.
("A")
C L
GROMMET
1/4 - 3/8 GAP
("F")
("C")
("C")
("B")
SECTION 5 – TECHNICAL DATA
EQUIPMENT
("E")
LD13763B
107
5 5

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents