DIP-switch inside the inverter to ON (move the left switch up). The DIP-switch is
located on the communication board and is marked SW1.
NOTE
Only the first and last SolarEdge devices in the chain should be terminated.
The other inverters in the chain should have the termination switch OFF
(down position).
 11. Tighten the nut of the COMM2 gland in a torque of 4 N*m.

RS485 Bus Configuration

To connect to the monitoring platform:
 1. Designate a single inverter as the connection point between the RS485 bus and the
monitoring platform. This inverter will serve as the leader inverter.
 2. Connect the leader to the monitoring platform using Ethernet (refer to Creating an
Ethernet (LAN) Connection above).
To configure the RS485 bus:
All inverters are configured by default as followers. To configure the leader:
 1. Make sure the inverter's ON/OFF/P switch is off.
 2. Make sure that the AC circuit breaker on the main distribution panel is on.
 3. Turn-on the on the DC Safety Unit .
 4. Access SetApp, as described in Communication on page 50.
 5. From the Commissioning screen, select Site Communication > RS485-1 > Protocol
> SolarEdge > SolarEdge Leader.
 6. Return to the RS485-1 screen and select Follower Detect.
Three Phase Inverter with SetApp Configuration
Chapter 5: Setting Up Communication with the Monitoring Platform
Figure 30: RS485 termination DIP-switch (SW1)
    46

Advertisement

Table of Contents
loading

This manual is also suitable for:

Se17k

Table of Contents