On-grid Commissioning of the inverter
When the inverter starts converting power after the initial connection to the AC, the
inverter enters Wake up mode until its working voltage is reached. This mode is
indicated by the flickering green inverter LED.
When working voltage is reached, the inverter enters Production mode and
produces power. The steadily lit green inverter LED indicates this mode.
4. Tap OK to return to the Commissioning menu.