NOTE
There are no LED indicators on the Ethernet connector, if the inverter is not
communicating with the Monitoring platform through a LAN refer to
"Troubleshooting Communication" on page 88
LAN Configuration
 1. The inverter is configured by default to LAN. If reconfiguration is required:
 a. Verify the ON/OFF/P switch is OFF.
 b. Verify the AC is on.
 c. Close the cover and turn ON the DC Disconnect Switch of the Synergy Manager.
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when
the Synergy Manager cover is removed.
AVERTISSEMENT!
RISQUE D'ÉLECTROCUTION, ne touchez pas les fils non isolés lorsque
le couvercle de l'onduleur est retiré.
 d. Use the SolarEdge SetApp to access the Commissioning main menu screen as
described in "Activating, Commissioning and Configuring the System" on
page 75"Activating, Commissioning and Configuring the System" on page 75 .
 e. From the Commissioning screen, tap Communication.
 f. Select Configure Ethernet, to configure the connection.
 2. Verify the connection, as described in "RS485 Bus Configuration" on page 73
NOTE
The system automatically establishes communication with the
monitoring platform as it is configured to LAN by default.
NOTE
If your network has a firewall, you may need to configure it to enable
the connection to the following address:
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx
Chapter 5: Setting Up Communication with the Monitoring
Destination Address: prodssl.solaredge.com
Modbus TCP Port: 443 (for incoming and outgoing data)