OFF (0) - Turning this switch OFF reduces the Power Optimizer Voltage to a low
safety Voltage and inhibits exportation of power. When this switch is OFF, the
Synergy Manager and Synergy Units control circuitry remains powered up.
P - Holding the switch pressed in P position allows performing the following
functions:
P Position duration
Switch moved to P for
less than 5 seconds, then
released.
Switch moved to P for
more than 5 seconds,
then released.
WARNING!
For inverters with manual Rapid Shutdown (PVRSS) functionality - Upon
PVRSS, the internal circuitry remains up, therefore the inverter cover must
be opened only after shutting off the inverter ON/OFF/P switch. This
disables the DC Voltage inside the inverter (Synergy Manager). Wait five
minutes before opening the cover. Otherwise, there is a risk of electric
shock from energy stored in the capacitors.
AVERTISSEMENT!
A la Coupure Rapide (PVRSS) les circuits internes restent actifs, ilest donc
impératif de n'ouvrir le couvercle qu'après avoir arrêté l'onduleur à l'aide de
l'interrupteur ON/OFF/P. Ceci coupe la tension DC à l'intérieur de
l'onduleur. Attendez cinq minutes avant d'ouvrir le couvercle. Sinon, il y a
risque d'électrocution du à l'énergie stockée dans les condensateurs.
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx
Chapter 3: Installing the Synergy Manager and Synergy
Function
Displays production information
for 5 seconds on the SetApp
screen.
Displays error type indications (if
exist) for 5 seconds.
Activates the Wi-Fi access point for
connecting to the SolarEdge
Inverter SetApp
Starts pairing
Units 36
Comments
While the switch
is in P, all LEDs
are ON