  Front Interface of Synergy Manager

Front Interface of Synergy Manager

DC Disconnect Switch
The DC Disconnect Switch is a manually operated safety switch for disconnecting the
DC power of the SolarEdge system.
NOTE
When the Synergy Manager is OFF (for example during maintenance) it may
be locked to prevent a safety hazard:
1. Move the switch to the Lock position.
2. Insert the lock through the knob opening
and lock.
 
ON/OFF/P Switch
Figure 10 shows the ON/OFF/P switch of the Synergy Manager.
ON (1) - Turning this switch ON (after Power Optimizer pairing) starts the operation
of the Power Optimizers, enables power production and allows the inverter to
begin exporting power to the utility grid.
Figure 9: Synergy Manager Unit - Front interfaces
Figure 10: ON/OFF/P switch
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx

Advertisement

Table of Contents
loading

This manual is also suitable for:

Se43.2kSe50kSe66.6kSe80kSe100kSe110k ... Show all

Table of Contents