SolarEdge SE K Series Installation Manual page 30

Three phase inverters with synergy technology
Hide thumbs Also See for SE K Series:
Table of Contents

Advertisement

Chapter 2: Installing the Power
Optimizers   29
For mounting on rails with sliding nut fasteners: If the star washer cannot be
used, use the SolarEdge grounding plate (purchased separately) between the
railing and the flat side of the mounting bracket. Use mounting specific hardware
as needed. Apply a torque of 9.5 N*m / 7 lb*ft.
See Figure 5 .
Figure 5: Power Optimizer installation and grounding using a grounding plate
For mounting on un-grounded structures (such as a wooden structure): If the
star washer or the plate cannot be used, use the SolarEdge grounding lug
(purchased separately) with an equipment-grounding conductor according to
the supplied instructions. The grounding terminal accepts a wire size of 6-14
AWG, and must be sized for equipment grounding per NEC 250.122
requirements. Tighten the screws connecting the Power Optimizer to the frame
and the grounding terminal screw. Apply a torque of 9.5 N*m / 7 lb*ft.
Figure 6: Power optimizer grounding terminal
Three Phase Inverters with Synergy Technology PN: SExxK-xxxxIxxxx

Advertisement

Table of Contents
loading

This manual is also suitable for:

Se43.2kSe50kSe66.6kSe80kSe100kSe110k ... Show all

Table of Contents