  Step 3: Verifying Proper Activation and Commissioning
Communication
Communication settings can be configured only after communication connections are
complete. Refer to Setting Up Communication with the Monitoring Platform on page 53.
From the Commissioning menu, select Monitoring Communication > Auto Select.
SetApp will automatically detect your connection method. Follow the on-screen
instructions to complete the configuration and establish communication with the
monitoring platform.
From the Commissioning menu, Select Site Communication to configure
communication between multiple SolarEdge devices or external non SolarEdge
devices, such as batteries or data loggers.
For more information on the Monitoring Platform, refer to "The Monitoring
Platform" section and to the Monitoring Platform web page at:
https://www.solaredge.com/products/pv-monitoring#/
For more information, see Configuring Communication with Other Devices on page
47 below.
Power Control
Power control options are detailed in the Power Control Application Note , available on
the SolarEdge website at:
note_power_control_configuration.pdf.
The Grid Control option may be disabled. Enabling it opens additional options in the
menu.
The Energy Manager option is used for setting power export limitation, as described in
the Export Limitation Application Note , available on the SolarEdge website at:
https://www.solaredge.com/sites/default/files/feed-in_limitation_application_note.pdf.
 
Step 3: Verifying Proper Activation and
Commissioning
 1. Select Information and verify that the correct firmware versions are installed on
each inverter. To save the information to a read-only file, tap the PDF icon (iOS) or
the JPEG icon (Android) at the bottom of the screen.
 2. Select Status and verify that inverter is operating and producing power.
 3. Verify that additional configurations were properly set by viewing the relevant
https://www.solaredge.com/sites/default/files/application_
SolarEdge Home Hub Inverter Single Phase MAN-01-00812-1.5