Status Screens - Operational Mode - SolarEdge SE3K-RWB Installation Manual

Table of Contents

Advertisement

56
  Status Screens - Operational Mode

Status Screens - Operational Mode

During normal operation pressing the external LCD light button turns on the LCD
backlight.
Additional presses display the following screens one after the other.
Initial Status
V a c [ V ] V d c [ V ] P a c [ W ]
2 4 0 . 7   3 7 1 . 9     2 3 4 9 . 3
P _ O K : X X X / Y Y Y < S _ O K >
                                                O N
Vac [V]: The AC output voltage
Vdc [V]: The DC input voltage
Pac [W]: The AC output power
P_OK: XXX/YYY: There is a connection to the power optimizers and at least one
power optimizer is sending monitoring data. XXX is the number of power optimizers
for which telemetries have been received in the last two hours. YYY is the number
of paired power optimizers identified during the most recent pairing process. If XXX
and YYY are not equal, there may be a problem in one or more power optimizers.
S_OK: The connection to the SolarEdge monitoring platform is successful (appears
only if the inverter is connected to the server).
ON/OFF: Indicates the position of the inverter ON/OFF switch.
Main Inverter Status
V a c [ V ] V d c [ V ] P a c [ W ]
2 4 0 . 7   3 7 1 . 9 3 2 1 0 . 0
F a c [ H z ] O P s _ O k T e m p
5 0 . 0     1 1
Vac [V]: The AC output voltage.
Vdc [V]: The DC input voltage.
Pac [W]: The AC output power.
Fac [Hz]: The AC output frequency.
OPs_Ok: Number of optimizers sending telemetries (indicating that they are paired)
Temp [C or F]: The inverter heat sink temperature
     
2 8 . 2