3. When the activation is complete, do one of the following:
Select Connect to Another Device to continue activating additional inverters.
Select Start Commissioning for pairing and other system configuration.
Step 2: Commissioning and Configuring the
Installation
This section describes how to use the SetApp menus for commissioning and
configuring the inverter settings.
Menus may vary in your application depending on your system type.
To access the Commissioning screen:
Do one of the following:
During first time installation: Upon activation completion, in the SetApp, tap Start
Commissioning.
If the inverter has already been activated and commissioned:
If not already ON - turn ON AC to the inverter by turning ON the circuit breaker
on the main distribution panel.
Open SetApp and follow the on-screen instructions (scan the inverter QR code,
move the ON/OFF/P switch to P position for 2 seconds and release).
The mobile device creates a Wi-Fi connection with the inverter and displays the
main Commissioning screen.
Setting Country, Grid and Language
The inverter must be configured to the proper settings in order to ensure that it
complies with the country grid code and functions.
1. From the Commissioning screen select Country & Grid.
2. From the Country & Grid drop-down list, select the required option and tap Set
Country & Grid.
3. From the Language drop-down list, select your language and tap Set Language.
Pairing
1. From the Commissioning menu, select Pairing.
2. Tap Start Pairing.
3. When Pairing Complete is displayed, the system startup process begins:
Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.4
Chapter 5: Activating, Commissioning and Configuring the System
41

Advertisement

Table of Contents
loading

Table of Contents