 6.  Select the following to configure the connection:
 
Server è LAN
l
 
RS485-1   è  Protocol è SolarEdge Master
l
 
RS485-1 è Slave Detect
l
The system starts automatic detection of the SolarEdge slave inverters connected to the master 
inverter. The inverter should report the correct number of slaves. If it does not, verify the connections 
and terminations.
Protocol 
Device ID
Slave Detect
Long Slave Detect
Slave List
 7.  To check the slave IDs and last communication time, select RS485-1 è Slave List.
 8.  Verify the connection of the master to the SolarEdge monitoring platform, as described in the next 
section.

Verifying the Connection

After connecting and configuring a communication option, perform the following steps to check that 
the connection to the monitoring server has been successfully established.
 1.  If the Connection Unit cover is not closed, close it: Attach the   C onnection Unit cover and secure it by 
tightening the screws with a torque of 10.3 N*m/ 7.5 lb.*ft.For proper sealing, first tighten the corner 
screws and then the two central screws.
 2.  Access the Status screen:
 a.  If not already ON - turn ON AC to the inverter by turning ON the circuit breaker on the main 
distribution panel. 
 b.  If not already ON - move the Connection Unit switch to the ON position.  
 c.  Open   S etApp and follow the instructions on the screen (scan the inverter bar-code; move the 
ON/OFF/P switch to P position (for less than 5 sec) and release). 
The mobile device creates a Wi-Fi connection with the inverter and displays the inverter main 
Status screen.
Three Phase Inverter with synergy technology Guide MAN-01-00402-1.1
RS485-1
SolarEdge (Master)
1
3 Slaves
3 Slaves
3 Slaves
Chapter 6: Setting Up Communication
 
65