INSTALLATION:

Set-up the masonry jobs creating an opening in the wall where
the frame will be installed (1), paying attention to envision the
space for the six slots for inserting the respective support fins
(2) and a space under the frame sufficient to carry out the kit
connections (Fig. 4).
N.B.: it is very important to provide a support screed (A) in
the area under the Super Trio Container at the support point
of the storage tank.
It is also possible to fix the frame to the wall with plugs (not
supplied) using the special four holes Ø 8 mm (6).
The Super Trio Container is closed by the side cover (5), where
the air intake grid is present, by the upper cover (3) where it
is possible to let the flue out and by the door (4) which can be
opened using the handle and only after having unlocked the
vertical locks in order to access the internal components.
Internally there are appendices (7) prepared for the attachment
of the various components.
Attention: The installation of the Super Trio Container inside
the wall, must guarantee a stable and effective support to the
appliance it contains. This kit only ensures adequate support
if it is inserted properly (according to good practice rules)
and positioned in square with respect to the wall following
the instructions given below, thus guaranteeing the correct
functionality of the front doors. The Super Trio Container is
not a supporting structure and cannot replace the piece of wall
removed. It is therefore necessary to check its correct positioning
inside the wall.
For safety reasons, it is necessary to carefully seal the housing
compartment of the Super Trio Container in the wall, in com-
pliance with Standards in force.
Make sure that the knockouts for the hydraulic connections
have been removed at the intended pipe path. Be sure to remove
the relevant sections based on the flue ("B type" and "C type"
installations) and the intake ducts (only for "C type" installation).
Make sure that the pre-cuts for the various connections have
been removed from the intended route.
Insert the frame inside its own seat, remembering to open the
six support fins (2) before inserting it.
After installing the frame, it is possible to insert the thermal kits
by hooking them to the provided hooks.
Now make the connections according to your needs.
Some holes are pre-cut smaller with respect to the useful size
in order to allow them to be enlarged according to your needs.
Once the frame has been installed, it is necessary to prepare
all the connections for the hydraulic connection to the specific
product selected in the lower and lateral part.
N.B.: The connection unit is not supplied, but is sold separately
(optional). To ease installation, choose whether to make the
connection at the rear, bottom or side (bottom right) of the
Container Super Trio (see Fig. 3).
For electrical connections, separate the connection to the
electricity grid and the connection to the temperature control
by passing the cables through the various openings provided.
Make the gas connection (where required). The gas pipe can
exit downwards, through the rear outlet, lower outlet, right side
outlet or from the front using the appropriate pre-cut already
provided on the door (see figures below).
Once out from the front, it is possible to turn the gas pipe in the
preferred direction.
N.B.: to install the gas supply pipe, under or out of route, comply
with the installation standards UNI 7129 / 7131-99.
Install the refrigerant gas circuit connection pipes using the
pre-drilled holes. The pipes must protrude inside the Solar
Container kit as much as necessary to allow connection to the
chosen product
N.B.: For the installation of the refrigerant gas circuit and
connection to the heat pump, comply with the UNI EN 378
Standards.
Attention: For assembly / installation and commissioning of the
various components inside the Super Trio Container, please refer
to the specific instruction booklet of each individual product.
Once the connections have been made, assemble the flue ac-
cording to the instructions in the boiler instructions manual.
Lastly, close the frame using the front door.
At this point, the installation is complete and the frame cover
can be painted according to requirements and taste.