Pre-commissioning when AC Power is Not Connected
1
Download SolarEdge SetApp
Download
5
Disconnect and remove power bank
6
Turn switches to OFF
7
Wait until inverter turns-off (all LEDs turn-off)
3
2
Turn ON
ON
Power bank: 60W
output port , USB-C
Power Delivery (PD):
20V 3A (not provided)
Connect power bank
1 meter, USB-C / USB-C (not provided)
15
(Option 1)
4
Start and follow SetApp
Start
Cover connector
when not used
MAN-01-00822-1.1
A
17