Running a Battery Self-test

You can run a battery self-test only after finishing the battery installation and
configuration (refer to the battery installation guide).
The purpose of the battery self-test is to check the battery's charge and discharge
functionality.
To run a battery self-test:
 1. Make sure the battery's circuit breaker switch is ON.
 2. Switch the inverter ON/OFF/P switch to ON.
 3. In SetApp, select Commissioning > Maintenance > Diagnostics > Self-Test >
Battery Self-Test > Run Test.
 4. Wait for all tests to complete and check the results in the summary table.
If any of the tests have failed, see the table below for possible solutions:
Test Results
Charge failed
Discharge failed
Communication
Inverter switch is off
To show the last test results:
Select Commissioning > Maintenance > Diagnostics > Self-Test > Battery Self-Test
> Show Last Results.

Enabling StorEdge Applications

This section describes how to configure your system to use StorEdge applications.
Before enabling StorEdge applications, make sure to:
Finish the battery installation and configuration (refer to the battery installation
guide)
Run a battery self-test, as described above
Single Phase Energy Hub Inverter with Prism Technology MAN-01-00842-1.3
Chapter 6: Activating, Commissioning and Configuring the System
Check that the power and communication cables
between the battery and inverter are properly
connected.
Check that the power and communication cables
between the battery and inverter are properly
connected.
Check that the communication cables between the
battery and inverter are properly connected.
Switch the inverter ON/OFF/P switch to ON.
Solution