Connecting The Backup Interface (Optional); Connecting An External Ct To The Energy Meter (Optional) - SolarEdge Energy Bank Installation Manual

Single phase inverter with prism technology
Hide thumbs Also See for Energy Bank:
Table of Contents

Advertisement

36
  Connecting the Backup Interface (Optional)

Connecting the Backup Interface (Optional)

The Backup Interface must be installed to allow the operation of batteries.
When connecting the Backup Interface to the inverter, use the following cable types:
Communication - 0.25 mm
12V power -
If the distance between the inverter and the Backup Interface is smaller than 15
m, use the CAT6 communication cable (see above).
If the distance is greater than 15 m, use a dedicated cable with a cross section of
2
1.5 mm
or greater.
To connect the Backup Interface:
 1. Connect the communication and 12V power cables to the Backup Interface, as
explained in the installation manual that comes with the Backup interface.
 2. Open Communication Gland 1 at the bottom of the Connection Unit.
 3. Feed the other end of the communication cable through one of the gland openings.
 4. Remove the 7-pin connector from the port labeled Backup Interface on the
communication board.
 5. Connect the communication cable wires to the 7-pin connector, as shown below.
 6. Close Communication Gland 1 to a torque of 5.5 N*m.
Connecting an External CT to the Energy Meter
(Optional)
To enable import/export or consumption metering, connect an external current
transformer (purchased separately from SolarEdge) to the Energy Meter.
2
2
(0.25–1.5 mm
Figure 16: Connecting the Backup Interface
Single Phase Energy Hub Inverter MAN-01-00812-1.1
), 600V insulated or CAT6