 4. Insert the meter wires into the connector as shown below and tighten them with the
screws.
 5. Connect the connector back to the RS485-1 port.
 6. Make sure the RS485-1 DIP switch (the left switch) on the inverter's communication
board is OFF.
 7. Terminate the Energy Meter by moving up the DIP switches, as shown above.

Connecting the Battery

WARNING!
The battery must be powered off before and during wiring.
For connecting the battery to the inverter, use copper cables with the following
parameters:
Maximum length: 5m
Cross-section area: 35 or 50 mm
Connecting DC Cables
 1. Make sure the battery circuit breaker is OFF.
 2. Make sure DC to the inverter is OFF.
 3. Strip the required length of the battery's DC cables.
 4. Crimp the supplied lugs on the power cables and tighten them with the heat shrinks.
StorEdge Three Phase Inverter MAN-01-00648-1.3
Chapter 5: Connecting the Inverter
Figure 14: Meter Connection 2
2
    36