To run a battery self-test:
 1. Make sure the battery's circuit breaker switch is ON.
 2. Switch the inverter ON/OFF/P switch to ON.
 3. In SetApp, select Commissioning è Maintenance è Diagnostics è Self-Test è
Battery Self-Test è Run Test.
 4. Wait for all tests to complete and check the results in the summary table.
If any of the tests have failed, see the table below for possible solutions:
Test Results
Charge failed
Discharge failed
Communication
Inverter switch is off
To show the last test results:
Select Commissioning è Maintenance è Diagnostics è Self-Test è Battery Self-
Test è Show Last Results.

Configuring StorEdge Applications

Maximize Self-consumption (MSC)
In this mode, the battery is automatically charged and discharged to meet consumption
needs.
The battery has two states:
OFF – the battery is in standby
ON – the battery is controlled for maximized self-consumption
Battery OFF periods can be configured to extend battery lifetime by minimizing the
number of shallow discharges (for example at nighttime or during the winter).
StorEdge Single Phase Inverter with HD-Wave Technology MAN-01-00627-1.1
Check that the power and communication cables
between the battery and inverter are properly
connected.
Check that the power and communication cables
between the battery and inverter are properly
connected.
Check that the communication cables between the
battery and inverter are properly connected.
Switch the inverter ON/OFF/P switch to ON.