Running A Battery Self-Test - SolarEdge StorEdge Installation Manual

Single phase inverter with hd-wave technology and setapp configuration
Hide thumbs Also See for StorEdge:
Table of Contents

Advertisement

 2. Access SetApp and select Commissioning èCommunication.
Server
LAN
RS485-1
RS485-2
ZigBee
Wi-Fi
Cellular
GPIO
Modbus
TCP port
 3. From the Communication screen, select RS485-2 è Protocol è Modbus (Multi-
Device).
 4. Return to the previous screen and select Add Modbus Device è Battery.
 5. Verify the battery information by selecting Battery 1 è Battery Information.
To set up communication with the Energy Meter:
If you are setting up communication with the meter before the battery, first perform
Steps 1-3 on page 40. After that, proceed with the steps below.
 1. In the RS485-2 screen, select Add Modbus Device è Meter.
 2. Set the Energy Meter's CT Rating according to the CT specifications. If the CT rating
value returns to 0, check communication with the CT.
 3. Select Meter 1 è Meter Function è Export+Import (E+I).

Running a Battery Self-test

Run a battery self-test to check the battery's charge and discharge functionality.
StorEdge Single Phase Inverter with HD-Wave Technology MAN-01-00627-1.1
Chapter 6: Activating, Commissioning and Configuring the System
Communication
LAN
DHCP
None
SolarEdge
Master
NA
NA
PCL 
RRCR
Disable
    41