30
  Connecting the AC Grid to the Inverter
WARNING!
Turn OFF the AC before connecting wires to the AC terminals. If
connecting equipment grounding wire, connect it before connecting the
AC Line and Neutral wires.
 6. Pass the AC Line and Neutral wires through the AC gland of the inverter and
connect them to the AC terminal block of the inverter.
 7. Connect the AC grounding wire to the grounding bar in the Connection Unit.
NOTE
The inverter's AC terminal block and Connection Unit's grounding bar are
connected with a grounding wire. Do not disconnect the wire on either
side!
 8. Tighten the screws of each AC terminal and the grounding bar with a torque of 1.2-
1.5 N*m / 0.88-1.1 lb*ft.
 9. Check that the wires are fully inserted and cannot be pulled out easily.
 10. Tighten the AC cable gland with a torque of 2.8-3.3 N*m / 2.0-2.4 lb*ft.
StorEdge Single Phase Inverter with HD-Wave Technology MAN-01-00627-1.1
Figure 13: AC cable connection