60
  Connecting to the Battery
Tie and wrap the cables to avoid pulling them out during mounting.
Adhere to all safety cautions and information in the battery documentation.
The battery connects to the DC side of the inverter. Since the inverter DC connections
are on its left side, it is recommended to position the battery to the left of the inverter
to simplify wiring.
WARNING!
The battery must be powered off before and during wiring.
To power off the battery:
 1. Turn off the circuit breaker.
 2. Turn off the disconnect/auxiliary power switch.
To power the battery back on:
 1. Turn on the disconnect/auxiliary power switch.
 2. Turn on the circuit breaker.
For details, see Powering the LG Chem Battery Off and On on page 147.
 
AVERTISSEMENT!
La batterie doit être éteinte avant et durant le câblage:
Pour éteindre la batterie:
 1. Fermez le disjoncteur.
 2. Fermez l'interrupteur auxiliaire.
 
Pour rallumer la batterie:
 1. Ouvrez l'interrupteur auxiliaire.
 2. Ouvrez le disjoncteur.
Pour plus de détails, consultez Powering the LG Chem Battery Off and On page
147.
 