Step 1: Activating the System
4. Verify that the inverter is configured to the proper country: Press the LCD light
button until reaching the ID status screen:
I D : # # # # # # # # # #
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
C P U : 0 0 0 3 . 1 9 x x
C o u n t r y : U S A 1
5. If required, perform the following additional steps before closing the inverter cover:
Country settings or inverter configuration using the internal LCD user buttons –
refer to Country and Grid on page 79.
Communication options connection – refer to Setting Up Communication to the
Monitoring Platform on page 96.
StorEdge application configuration - refer to System Configuration on page 109.
6. Close the inverter cover by tightening the screws with a torque of . For proper
sealing, first tighten the corner screws and then the two central screws. The
following figure illustrates recommended order:
7. Close the StorEdge Connection Unit internal cover: Attach the cover and secure it by
tightening the four screws with a torque of 1.2 N*m / 0.9 ft.*lb.
8. Make sure the AC Bypass switch in the StorEdge Connection Unit is switched to the
left (position 1).
9. Make sure the backed-up loads AC breaker in the StorEdge Connection Unit is UP.
Figure 19: Tightening order of the screws