Chapter 6: Commissioning the Installation
45
Chapter 6: Commissioning the Installation
This chapter describes how to activate the system, pair the poweroptimizers to the
inverter and verify the proper functioning of the system.
Removing the Inverter Cover
1. Switch the inverter ON/OFF/P switch to OFF. Wait 5 minutes for the capacitors to
discharge.
StorEdge Solution with Backup MAN-01-00262-1.5