  Installation Guidelines
Frame-mounted power optimizers are mounted directly on the
module frame , regardless of racking system (rail-less or with rails).
For installation of frame-mounted power optimizers, refer to
http://www.solaredge.com/sites/default/files/installing_frame_mounted_
power_optimizers.pdf
The power optimizer can be placed in any orientation.
If connecting more modules than optimizer inputs in parallel, use a branch cable.
Some commercial power optimizer models have a dual input.
Position the power optimizer close enough to its module so that their cables can be
connected.
Make sure to use power optimizers that have the required output conductor length:
Do not use extension cables between a module and a power optimizer,
between two modules connected to the same optimizer, or between two
optimizers other than in the cases specified below.
You can use extension cables between power optimizers only from row to row,
around obstacles within a row, and from the end of the string to the inverter, as
long as the maximum distance is not exceeded.
Completely shaded modules may cause their power optimizers to temporarily shut
down. This will not affect the performance of the other power optimizers in the
string, as long as the minimum number of unshaded power optimizers connected in
a string of modules is met. If under typical conditions fewer than the minimum
optimizers are connected to unshaded modules, add more optimizers to the string.
Equipment grounding tightening torques: 4-6 AWG: 45 lb-in, 8 AWG: 40 lb-in, 10-14
AWG: 35 lb-in.
To allow for heat dissipation, maintain a 2.5 cm / 1" clearance distance between the
power optimizer and other surfaces, on all sides except the mounting bracket side.
.