  Viewing System Status
Inverter Energy Status
Displays the total energy produced during the last day, month, year and since inverter
installation.
Inverter Energy
Today
45 kWh
Total: 41.03 MWh
Today: Since midnight
This Month: Since 1st of the current month
This Year: Since January 1st
Total (Wh): The inverter total energy. If an external meter is installed, the value
displayed in this line depends on the meter type connected to the inverter and its
location:
If a bidirectional meter is connected at the consumption point, this value is the
consumed energy.
If the meter is installed at the production point, this value is the energy
produced by the site.
If the meter is installed at the grid connection point, this value is the energy
exported to the grid.
This Month
This Year
1.14 MWh
13.68 MWh
 
 