47
  Viewing System Status
Site Status
The Site status screen shows the accumulated status of all inverters connected to a
master inverter in a chain (bus) and the master inverter status.
Production
1.00 MW
Power
100 kW
P_OK: 141 0f 141
Optimisers Connected
Status
Production
CosPhi
1.00
Switch Off. Production disabled
Commissioning
Site status:
Production: The AC output power
Limit: Limitation setting (Export or Production)
Inverters: Number of connected inverters in the cluster, including the master
 
Status
Site
Limit
Inverters
1.00 MW
10/10
Inverter
SN 07318000C
Voltage
Frequency
277 Vac
60.9 Hz
S_OK
Server Connected
Switch
OFF
Limit
Country
Export
ITA
       ›
StorEdge Three Phase Inverter Installation Guide MAN-01-00648-1.1