Configuring StorEdge Applications

Maximize Self-consumption (MSC)
In this mode, the battery is automatically charged and discharged to meet consumption
needs.
The battery has two states:
OFF – the battery is in standby
ON – the battery is controlled for maximized self-consumption
Battery OFF periods can be configured to extend battery lifetime by minimizing the
number of shallow discharges (for example at nighttime or during the winter).
To set up maximize self-consumption:
 1. Access SetApp and select Commissioning è Power Control.
 2. Select Energy Manager è Energy Control è Maximum Self Consumption.
 3. Optionally, set the battery OFF periods as follows:
 a. Select Set Operation, and then select a month from the list that appears.
 b. Select a month. A list of options is displayed.
 c. Select one of the options:
Select Always OFF to avoid battery usage entirely (for example during
winter)
Set Start Time and End Time to set battery usage in specific hours and
avoid usage during specific hours throughout the month (for example at
night). This sets the periods during which the battery will be in the OFF
state.
Select Always ON to use battery at all times for charging/ discharging.

Viewing System Status

During normal operation, the Status screen displays all the inverter settings and
operation status. Scroll up or down to display various status parameters as described in
the following sections.
The LED indication provides more information about system performance; Refer to
To access the Status screen:
From the Commissioning menu select Status. The main inverter Status screen is
displayed (see below).