41
  Step 2: Commissioning and Configuring the Installation
The Energy Manager option is used for setting power export limitation, as
described in the Export Limitation Application Note , available on the
SolarEdge website at
in_limitation_application_note.pdf.
 
Device Manager
From the Commissioning menu, select Device Manager to configure various system
Smart Energy Management devices.
For more information refer to
https://www.solaredge.com/products/device-control#/.
Maintenance
From the Commissioning menu, select Maintenance to configure various
system settings, as described below.
Date and Time: Set the internal real-time clock. If connected to the monitoring
platform, the date and time are set automatically and only time zone should be set.
Reset Counters: Resets the accumulated energy counters that are sent to the
monitoring platform.
Factory Reset: Performs a general reset to the default device settings.
Arc Fault Circuit Interrupter (AFCI): Enables or disables production interruption in
case of arc-fault, sets the reconnection mode, and enables or disables manual
AFCI self-test.
Refer to
https://www.solaredge.com/sites/default/files/arc_fault_
detection_application_note.pdf
Firmware Upgrade: Perform a software upgrade.
Diagnostics: Displays the Isolation status and power optimizer status
screens. Refer to
https://www.solaredge.com/sites/default/files/application_note_
isolation_fault_troubleshooting.pdf.
Activate Standby Mode: Enables/disables Standby Mode - for
remote commissioning.
Board Replacement: Backs up and restores the system parameters, including
energy counters; Used during board replacement according to the instructions
supplied with replacement kits.
https://www.solaredge.com/sites/default/files/feed-
.
StorEdge Three Phase Inverter Installation Guide MAN-01-00648-1.1