Chapter 6: Activating, Commissioning And Configuring The System; Step 1: Activating The Installation - SolarEdge StorEdge Installation Manual

Three phase inverter with setapp configuration
Hide thumbs Also See for StorEdge:
Table of Contents

Advertisement

37
  Chapter 6: Activating, Commissioning and Configuring the System
Chapter 6: Activating, Commissioning and
Configuring the System
You can connect communication options at this stage, as described in Setting Up
Communication to the Monitoring Platform on page 52.
Once all connections are made, the system should be activated and commissioned
using the Inverter SetApp mobile application. You can download the app from the
Apple App Store and Google Play prior to reaching the site.
Internet connection is required for the download and for the one-time registration,
however not required for using the SetApp.

Step 1: Activating the Installation

During system activation, a Wi-Fi connection is created between the mobile device and
the inverter and the system firmware is upgraded.
Before activation - download, register (first time only) and log-in to SetApp on your
mobile device. Internet connection is required for the download and for the one-time
registration. Verify that the application is updated with the latest version.
1. Turn ON the AC circuit breaker on the main distribution panel.
To activate the inverter:
2. Open SetApp and follow the instructions on the screen (scan the inverter bar-code;
move the ON/OFF/P switch to P position for 2 seconds and release). SetApp creates
a Wi-Fi connection, upgrades the inverter CPU firmware and activates the inverter.
StorEdge Three Phase Inverter Installation Guide MAN-01-00648-1.1

Advertisement

Table of Contents
loading

Table of Contents