Adding, Removing, Or Replacing Power Optimizers - SolarEdge SE5K Installation Manual

Three phase system with setapp configuration for europe and apac
Hide thumbs Also See for SE5K:
Table of Contents

Advertisement

Adding, Removing, or Replacing Power Optimizers

 1. Turn OFF the inverter ON/OFF/P switch, and wait until the green LED is blinking ,
indicating that the DC voltage is safe (<50V), or wait five minutes before continuing
to the next step.
 2. Disconnect the AC to the inverter by turning OFF the circuit breakers on the
distribution panel.
 3. Turn OFF the DC Safety Unit (if applicable).
 4. Disconnect and connect the necessary power optimizers.
 5. Perform pairing and other procedures described in Activating, Commissioning and
Configuring the System Using the Inverter SetApp on page 35 on all inverters to
which power optimizers were added or from which power optimizers were removed.
 6. In the monitoring platform, use the Replace button in the logical
layout tab (in site Admin). Replace the serial number of the removed
power optimizer with the serial number of the newly installed power
optimizer. Refer to
monitoring-portal-site-admin.pdf
Three Phase System Installation Guide MAN-01-00505-1.2
Appendix F: Replacing and Adding System Components
https://www.solaredge.com/sites/default/files/se-