Figure 34 - Installation Of Durulene Vibration Isolators - York YCAL0019 Installation, Operation And Maintenance Manual

Air-cooled liquid chillers hermetic scroll
Table of Contents

Advertisement

FORM 150.67-NM1
ISSUE DATE: 4/28/2017
INSTALLATION OF DURULENE VIBRATION ISOLATORS
1. Read instructions in their entirety before begin-
ning installation.
2. Isolators are shipped fully assembled and are to be
positioned in accordance with the submitial draw-
ings or as otherwise recommended.
3. Set isolators on floor, housekeeping pad, or sub-
base, ensuring that all isolator center lines match
the equipment mounting holes. The VMC group
recommends that the isolator base ("A") be in-
stalled on a level surface. Shim or grout as re-
quired, leveling all isolator bases to the same el-
evation (1/32 of an inch maximum difference can
be tolerated).
D

FIGURE 34 - INSTALLATION OF DURULENE VIBRATION ISOLATORS

JOHNSON CONTROLS
Units shipped on or after June 15, 2008
("B")
D
C L
4. Bolt or anchor all isolators to supporting structure
utilizing base thru holes ("B").
5. Remove top bolt and top washer. Place equip-
ment on top of isolators so that mounting holes
in equipment or base line up with threaded hole
("C").
6. Reinstall top bolt and washer and tighten down.
7. Installation is complete.
("C")
C L
SECTION D-D
SECTION 5 – TECHNICAL DATA
TOP BOLT
TOP WASHER
("B")
("A")
LD13762B
139
5 5

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents