Power Optimizer Troubleshooting

Power Optimizer Troubleshooting
If the inverter status screen indicates that not all power optimizers are paired or not all 
are reporting (P_OK xxx/yyy, and x<y), those optimizers can be identified through the 
LCD. Refer to https://www.solaredge.us/sites/default/files/non_reporting_power_
optimizers.pdf
Pairing failed
String voltage is 0V
String voltage not 0V but lower than number of optimizers 
68
Single Phase Inverter with HD-Wave Technology Installation MAN-01-00306-1.1
Problem
Possible cause and
troubleshooting
Power optimizers are shaded.
 If you connected the inverter to the   m onitoring 
platform, retry pairing remotely (during 
sunlight). Make sure to leave the inverter 
ON/OFF switch ON and that S_OK appears in 
the status screen.
Power optimizer (s) output is disconnected.
Connect all power optimizer outputs.
Power optimizer(s) not connected in the string.
Connect all power optimizers
Module(s) not connected properly to power 
optimizer inputs (not applicable to smart 
modules).
Connect the modules to the optimizer inputs
String reverse polarity.
Check string polarity using a voltmeter and 
correct if needed.