Chapter 5: Commissioning the Installation
iPhone
Use the Mapper smartphone application to scan the power optimizer and inverter 2D bar-codes. This 
application creates an XML file that can be uploaded to the   m onitoring platform during site registration. 
The Mapper can be downloaded from the application stores.
For detailed information, refer to the Mapper Software Guide or to the Site Mapper demo 
movie, available on the SolarEdge website at http://www.solaredge.us/groups/installer-
tools/site-mapper.
 
 

Creating a Site in the Monitoring Platform

Create the site in the monitoring platform using the registration form available at  
https://monitoring.solaredge.us/solaredge-web/p/login. Fill out all required information 
in the form, which includes information about your installation, as well as details about 
its logical and physical mapping.
 

Paper Template

Fill out the Physical Layout Template (downloadable from the SolarEdge site) using the 
detachable 2D barcode stickers on each power optimizer. Once the form is completed, 
scan it and upload the scanned file to the   m onitoring platform during site registration. 
For an example paper template, refer to http://www.solaredge.us/files/pdfs/physical-
layout-template.pdf.
 