Chapter 5: Commissioning the Installation
Chapter 5: Commissioning the Installation
This chapter describes how to activate the system, pair the poweroptimizers to the inverter and verify
the proper functioning of the system.
Step 1: Activating the System
1. Verify that the inverter ON/OFF switch is OFF.
2. If not already removed, remove the inverter cover: Open the inverter cover's six Allen screws and
carefully pull the cover horizontally before lowering it.
WARNING!
ELECTRICAL SHOCK HAZARD. Do not touch uninsulated wires when the inverter cover is
removed.
AVERTISSEMENT!
RISQUE D'ÉLECTROCUTION, ne touchez pas les fils non isolés lorsque le couvercle de l'onduleur
est retiré.
3. Activate the inverter:
a. Verify that the card S/N matches the inverter S/N.
b. Insert the card into the slot marked "CARD" on the communication board.
c. Turn AC ON.
d. LCD shows: Running Script... è Done!
If LCD shows: Failed:
Turn AC OFF and ON (reset), and repeat the activation process.
l
Use the activation code that appears on the certification inverter label to manually activate the
l
inverter.
If the problem persists, contact SolarEdge Support.
l
NOTE
You can use the activation code that appears on the certification inverter label to activate
the inverter in case of a script error or a missing activation card.
4. Verify that the inverter is configured to the proper country: Press the up or down buttons until
reaching the ID status screen:
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
C P U : 0 0 0 3 . 1 9 x x
C o u n t r y : U S A 1
32
Single Phase Inverter with HD-Wave Technology Installation MAN-01-00306-1.1
Figure 19: Communication board and activation card