Step 3: Verifying Proper Operation; Step 4: Reporting And Monitoring Installation Data; The Solaredge Monitoring System - SolarEdge StorEdge SE5000-xxS0 series Installation Manual

For single battery or high capacity
Table of Contents

Advertisement

Step 3: Verifying Proper Operation

After the wake-up time is over, a status screen similar to the following appears on the inverter LCD panel:
V a c [ V ]
2 4 0 . 7
P _ O K :
. . . . . . . . . . . . . . . . .
 1. Verify the following: 
The green inverter LED is steadily lit.
l
The ON/OFF indicator on the LCD panel reads ON.
l
P_OK: XXX/YYY:   T here is a connection to the power optimizers and at least one power optimizer is 
l
sending monitoring data. Optimizers send telemetries in a frequency of up to 10 minutes.
S_OK appears, if the inverter is connected to the SolarEdge monitoring portal.
l
Vac [V] specifies the measured grid AC output voltage.
l
Vdc [v] : Specifies the DC input voltage, which should equal the sum of the output voltages of all 
l
modules (and should be within the operating range of the inverter).
Pac [W] specifies the AC output power produced.
l
 2. Take note of the serial # on the inverter label using the detachable 2D barcode sticker on each device.
This information is used in the SolarEdge monitoring portal to identify this inverter and is needed to
open a new site in the monitoring portal.
Your SolarEdge power harvesting system is now operational.

Step 4: Reporting and Monitoring Installation Data

NOTE
This step requires connecting one of the communication options. Refer to Setting Up
Communication to the Monitoring Portal on page 59.

The SolarEdge Monitoring System

The SolarEdge cloud-based monitoring platform (monitoring portal)   e nables accessing 
SolarEdge site information, including up-to-date information viewed in a physical or 
logical view. The monitoring portal is described in detail in the SolarEdge Monitoring Portal 
User Guide, available on the SolarEdge website at 
http://www.solaredge.com/files/pdfs/solaredge-monitoring-portal-user-guide.pdf. The 
SolarEdge monitoring portal can display logical and physical layouts of the installed 
system, as follows:
Logical Layout: Shows a schematic logical layout of the components in the system, such as: inverters, 
l
strings and modules, as well as their electrical connectivity. This view enables you to see which 
modules are connected in each string, which strings are connected to each inverter, and so on.
Physical Layout: Shows a schematic physical layout of the components in the system, such as: 
l
inverters, strings and modules, as well as their electrical connectivity. This view enables a bird's eye 
view of the actual location of a system component.
SolarEdge-StorEdge -Single Battery/High Capacity Installation MAN-01-00283-1.1
V d c [ V ]
P a c [ W ]
3 7 1 . 9
2 3 4 9 . 3
X X X / Y Y Y
< S _ O K >
O N
Chapter 6: Commissioning the Installation
39

Advertisement