Chapter 4: Installing the Backed-up Loads Panel and Meter
Chapter 4: Installing the Backed-up Loads
Panel and Meter
This chapter describes installation of the backed-up loads panel and a meter.
Installing the Backed-up Loads Panel
Install a secondary AC panel for backed-up loads (not supplied by SolarEdge). Rewire the backed-up loads
through this panel.
Install one pole 25A as the main circuit b reaker.
Figure 10: Backed-up Loads Panel
22
SolarEdge StorEdge -Single Battery/High Capacity Installation MAN-01-00283-1.1