Step 1: Activating the System
C P U : 0 0 0 3 . 1 9 x x
C o u n t r y : E S P
 6.  If required, perform the following additional steps before closing the inverter cover:
Country settings or inverter configuration using the internal LCD user buttons – refer to 
 
Country and Grid on page 57.
Communication options connection – refer to Setting Up Communication to the Monitoring 
 
Platform  on page 70.
StorEdge application configuration - refer to System Configuration on page 80.
 
 7.  Close the inverter cover   b y tightening the screws with a torque of 9.0 N*m/ 6.6 lb*ft. For proper 
sealing, first tighten the corner screws and then the two central screws. The following figure 
illustrates recommended order:
 8.  Close the StorEdge Connection Unit internal cover: Attach the cover and secure it by tightening the 
four screws with a torque of 1.2 N*m / 0.9 ft.*lb. 
 9.  Make sure the AC Bypass switch in the StorEdge Connection Unit is switched to the left (position 1).
 10.  Make sure the backed-up loads AC breaker   i n the StorEdge Connection Unit is UP. 
 11.  Close the StorEdge Connection Unit external cover: Attach the cover and secure it by tightening the 
six screws with a torque of 1.2 N*m / 0.9 ft.*lb. 
44
Figure 32: Tightening order of the screws
Figure 33: StorEdge Connection Unit
StorEdge Inverter Installation Guide MAN-01-00390-1.1

Advertisement

Table of Contents
loading

Table of Contents