 9.  Unscrew the two conduit nuts securing the StorEdge Connection Unit to the external conduits. 
 10.  Release the bracket securing the StorEdge Connection Unit to the wall.
 11.  Carefully remove the StorEdge Connection Unit with its mounting bracket from the wall.

Installing a New StorEdge Connection Unit

 1.  Open the StorEdge Connection Unit cover.
 2.  Position the new StorEdge Connection Unit below the inverter and from the inside of the inverter 
grab the AC and DC wires extending from the unit conduits, as shown below:
 3.  Attach the StorEdge Connection Unit with its bracket to the wall and slightly close the screws. Do not 
over tighten. 
 4.  For RGM inverters - Insert the meter RS485 cable through the DC side conduit of the StorEdge 
Connection Unit and connect to the inverter communication board.
 5.  Reconnect the cable from the inverter digital board to the StorEdge Connection Unit.
 6.  Reconnect all the external wires and ferrite beads..
 7.  Securely screw the two conduit nuts onto the conduit ends in the inverter.   V erify proper conduit 
sealing.
 8.  Close the StorEdge Connection Unit cover. Attach the cover and secure it by tightening the six screws 
with a torque of 1.2 N*m / 0.9 ft.*lb.
 
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0
Figure 43: Inserting the AC and DC conduits
Appendix B: Replacing and Adding System Components