Step 1: Activating the System
 3.  Activate the inverter according to the activation instructions supplied in the inverter package:
 a.  Verify that the card S/N matches the inverter S/N.
 b.  Insert the card into the slot marked "CARD" on the communication board.
 c.  Turn AC ON.
 d.  LCD shows: Running Script... è Done!
 e.  If LCD shows: Script error, contact SolarEdge Support.
 4.   Verify that the inverter is configured to the proper country: Press the LCD light button until reaching 
the ID status screen: 
I D :
# # # # # # # #
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
C P U : 0 0 0 3 . 1 4 x x
C o u n t r y : U S A 1
 5.  If required, perform the following additional steps before closing the inverter cover:
 
Country settings or inverter configuration using the internal LCD user buttons – refer to Country 
l
and Grid on page 45.
 
Communication options connection – refer to Setting Up Communication to the Monitoring Portal 
l
on page 71.
 
StorEdge application configuration - refer to System Configuration on page 62.
l
 6.  Close the inverter cover   b y tightening the screws with a torque of 9.0 N*m/ 6.6 lb*ft. For proper 
sealing, first tighten the corner screws and then the two central screws. The following figure 
illustrates recommended order:
 7.  Make sure the AC Bypass switch is switched to the left (position 1).