 3. Attach each power optimizer to the rack using the M6 (1/4'') stainless steel bolts, nuts and washers.
Apply torque of 9.5 N*m / 7 lb*ft. For 3NA series power optimizes, SolarEdge recommends mounting 
the power optimizer on a rail with the smooth side facing out, so that the power optimizer body will 
prevent its rotation.
 4. Use the following methods to ground the power optimizer
WARNING!
The metallic enclosure of the power optimizer must be grounded in accordance with the
requirements of the local and national codes.
L'enceinte métallique de l'optimiseur de puissance doit être mise à la terre en accord avec les
régulations locales et nationales.
For mounting on a grounded metal rail: Use the provided 5/16'' stainless steel grounding star 
l
washer between the railing and the flat side of the mounting bracket.   T he grounding washer 
should break through the anodize coating of the railing to ensure low resistive connection. Apply 
torque of 9.5 N*m / 7 lb*ft.
Figure 2: Power optimizer installation and grounding using a star washer
For mounting on rails with sliding nut fasteners: If the star washer cannot be used, use the 
l
SolarEdge grounding plate (purchased separately) between the railing and the flat side of the 
mounting bracket.   A pply torque of 9.5 N*m / 7 lb*ft.
Figure 3: Power optimizer installation and grounding using a grounding plate
1 For a list of racking models and their appropriate grounding method, refer to
http://www.solaredge.us/files/pdfs/grounding_se_power_optimizers.pdf
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.0
Chapter 2: Installing the Power Optimizers
1
:
.
13

Advertisement

Table of Contents
loading

Table of Contents