Step 3: Verifying Proper Activation

W a k i n g
R e m a i n i n g :
The countdown indicates the seconds remaining until entering the Production mode. This time is in 
accordance with local regulations and is typically between three to five minutes. 
When countdown is complete, the inverter enters Production mode and produces power. The steadily 
lit green inverter LED indicates this mode.
Step 3: Verifying Proper Activation
After the wake-up time is over, a status screen similar to the following appears on the inverter LCD panel:
V a c [ V ]
2 4 0 . 7
3 7 1 . 9
P _ O K :
X X X / Y Y Y
. . . . . . . . . . . . . . . . .
 1.  Verify the following: 
 
The green inverter LED is steadily lit.
l
 
The ON/OFF indicator on the LCD panel reads ON.
l
 
P_OK: XXX/YYY:   T here is a connection to the power optimizers and at least one power optimizer is 
l
sending monitoring data. Optimizers send telemetries in a frequency of up to 10 minutes.
 
S_OK appears, if the inverter is connected to the SolarEdge monitoring platform. 
l
 
Vac [V] specifies the measured grid AC output voltage. 
l
 
Vdc [v] specifies the DC input voltage, which should be approximately the inverter DC voltage (model 
l
dependent; refer to the inverter datasheet)
 
Pac [W] specifies the AC output power produced.
l
 2.  Take note of the serial number on the inverter label using the detachable 2D barcode sticker on each 
device. This information is used in the SolarEdge monitoring platform to identify this inverter.
Your SolarEdge power harvesting system is now operational.

Step 4: Reporting and Monitoring Installation Data

NOTE
This step requires connecting one of the communication options. Refer to Setting Up
Communication to the Monitoring Platform on page 72.

The SolarEdge Monitoring System

The SolarEdge cloud-based monitoring platform (monitoring platform)   e nables 
accessing SolarEdge site information, including up-to-date information viewed in a 
physical or logical view. The monitoring platform is described in detail in the SolarEdge 
Monitoring Platform User Guide, available on the SolarEdge website at 
http://www.solaredge.us/files/pdfs/solaredge-monitoring-platform-user-guide.pdf. 
The SolarEdge monitoring platform can display logical and physical layouts of the 
installed system, as follows:
 
Logical Layout: Shows a schematic logical layout of the components in the system, such as: inverters, 
l
strings and modules, as well as their electrical connectivity. This view enables you to see which 
modules are connected in each string, which strings are connected to each inverter, and so on.
50
U p . . .
0 5 1
S e c
V d c [ V ]
P a c [ W ]
2 3 4 9 . 3
< S _ O K >
O N
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.3