 1. Turn OFF the inverter ON/OFF switch, and wait until the LCD indicates that the DC voltage is safe 
(<50V), or wait five minutes before continuing to the next step.
WARNING!
If you cannot see the inverter panel, or if a malfunction is indicated on the LCD panel, wait five
minutes for the input capacitors of the inverter to discharge.
Si vous ne pouvez pas voir l'écran de l'onduleur ou si un dysfonctionnement est indiqué sur l'écran
LCD, attendez cinq minutes pour que les condensateurs d'entrée de l'onduleur soient déchargés.
 2. Turn OFF the Connection Unit and the AC switch of the distribution panel.
 3. Open and remove the Connection Unit cover.
 4. Open and remove the transparent internal cover.
 5. Remove the battery from the upper board of the Connection Unit and replace with a new standard
9V battery.
 6. Close the Connection Unit covers.
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.3
Appendix C: Replacing and Adding System Components
Figure 47: The battery holder
105

Advertisement

Table of Contents
loading

This manual is also suitable for:

Seauto-tx-5000

Table of Contents