SolarEdge SE3000 Installation Manual page 34

Hide thumbs Also See for SE3000:
Table of Contents

Advertisement

3
If the site is installed with an external DC switch between the power
optimizers and the inverter(s), then turn it ON.
4
Verify that P_OK appears, which indicates a connection to the power
optimizers. The number 0 indicates that no power optimizer has been paired
to this inverter. If you are re-pairing the power optimizers and inverters, the
number indicates the number of power optimizers that have been paired in
the past. If P_OK does not appear, check the power optimizer, strings and
DC input connections.
5
If the inverter is connected to the SolarEdge Monitoring server, verify that
S_OK appears. This denotes that the connection to the server is successful.
6
Verify that the Vac [v] on the LCD panel specifies the grid's correct AC
output voltage, in Volts.
7
Verify that the Vdc [v] on the LCD panel specifies the DC input voltage, in
Volts. There should be a safety voltage of 1 V for each power optimizer
connected to the inverter.
NOTE:
A measurement error on the inverter LCD of ±3 V is OK.
NOTE:
If the LCD panel shows 0 V:
Verify that the PV modules are are not shaded or otherwise obstructed.
Check for proper power optimizer, string and DC input connection.
Verify the correct polarity of the DC input connection.
8
Verify that Pac [w] on the LCD Panel specifies 0 as the AC output power, in
Watts. This is because the inverter is still off.
WARNING!
Verify that the ON/OFF indicator on the LCD panel, described above, reads OFF.
SolarEdge Installation Guide – MAN-01-00057-2.0
Commissioning the Installation
34

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents