DIP Switch Setup
DIP Switch Setup
Verify that the DIP switches on the system components are set as described in this section, according to 
the system hardware configuration. 
DIP Switch Setup in Meter and Inverter
Termination and bias guidelines:
 
The last external meter in the RS485 chain should be terminated with 120 Ohm (either internal or 
l
external).
 
Inverter communication board (Figure 22): 
l
 
If a meter is installed: No termination - SW7 Down
o
 
If a meter is not installed: termination ON - SW7 Up (see also Creating an RS485 Bus Connection on
o
page 74)
Figure 22: RS485 termination switch on the inverter communication board