WARNING!
The battery should be powered OFF before and during wiring. Turn OFF:
The auxiliary power supply switch
l
The circuit breaker switch
l
La batterie doit être étteinte avant et pendant le câblage. Fermer: 
Le commutateur d'alimentation auxiliaire 
l
Le commutateur du coupeur 
l
The following table,     a nd Figure 21 detail cable types and connections of one battery (LG-
chem Resu10H). For additional battery types and connection options, refer to Additional 
Battery Connections on page 104 or 
http://www.solaredge.com/sites/default/files/storedge_inverter_wiring_and_onsite_
checklist_na.pdf. Prepare cables and connect as described in the following table:
StorEdge
Connection Unit
connection
DC
BAT + terminal block
BAT - terminal block
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.2
LG Chem
Connection method
RESU10H
battery
StorEdge Connection
connection
Insert a flat blade
o
screwdriver into the
square opening at the top
DC+
of the terminal block and
press to open clamp
mechanism.
Insert the wire into the
o
round opening and
DC-
release the screwdriver
to spring back and clamp
the wire.
Chapter 5: StorEdge Inverter Connections
Recommended cable
to the
(min-max AWG)
Unit
DC cable 10 AWG (10-14
AWG), 600V insulated.