AC and DC conduit entries: Connection points of the Safety Switch.
l
 
AC and DC conduit entries: Connection points of the StorEdge Connection Unit.
l
 
ON/OFF switch: Turning this switch ON starts the operation of the power optimizers, enables power 
l
production and allows the inverter to begin exporting power to the utility grid/backed-up loads. 
Turning it OFF reduces the power optimizer voltage to a low safety voltage and inhibits exportation of 
power. When this switch is OFF, the inverter control circuitry remains powered up.
 
LCD light button: Pressing this button lights up the LCD for 30 seconds. In addition, you can press 
l
this button to view inverter status screens and access configuration menu options, as described 
Configuring the Inverter Using the LCD Light Button on page 55.
 
Two communication glands, for connection of inverter communication options. Each gland has 
l
three openings. Refer to Setting Up Communication to the Monitoring Platform on page 69 for more 
information.

StorEdge Connection Unit

The StorEdge Connection Unit     i ncludes:
 
DC safety switch: disconnects both the positive and negative conductors of the PV and the positive 
l
and negative conductors of the battery.
 
Openings for conduit entry: Four openings are ready to use and have sealing covers. Two openings 
l
are closed with knockouts. If required, open the knockouts as described in Opening Conduit Knockouts 
on page 96. 
 
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.2
Figure 9: StorEdge Connection Unit
Chapter 3: Installing the Inverter
23

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents